Artificial Intelligence Model to Assess Project Baseline Plan

Faculty Engineering Year: 2020
Type of Publication: ZU Hosted Pages:
Authors:
Journal: INTERNATIONAL JOURNAL OF SCIENTIFIC & ENGINEERING RESEARCH IJSER Volume:
Keywords : Artificial Intelligence Model , Assess Project Baseline    
Abstract:
Planning is one of the most important stages in managing construction projects. Most researches focus on developing and improving scheduled techniques. Yet, surveying the literature reveal insufficiency in the area of project planning assessment researches. This research aims at bridging this gap and introduce a model to assess Project Baseline Plan (PBP). The development of the PBP model is achieved in four steps. First, collecting factors affecting the Project Baseline Plan from literature. Second, identifying the most important factor using Delphi technique. Third, assigning relative weights to each factor using the Analytical Hierarchy Process (AHP). Fourth, developing and validating the PBP model. This model helps the user to predict the percentage of matching between the preconstruction program and the actual construction program. Both deterministic model and fuzzy model have been developed where the fuzzy model produces better results than the deterministic model. This research uses project duration as a bench mark to evaluate the model by comparing the model results for two case studies.
   
     
 
       

Author Related Publications

  • Ahmed Hessien Mahmoud Mohamed Elyamany, "Developing A Quality Measure For Evaluating The Contractor Performance Ii Asphalt Pavement Construction", Chinese Society of Pavement Engineering, 2013 More
  • Ahmed Hessien Mahmoud Mohamed Elyamany, "Using MEPDG to Develop Rational Pay Factor for Hot Mix Asphalt Construction", International Organization Of Scientific Research, 2013 More
  • Ahmed Hessien Mahmoud Mohamed Elyamany, "Effect of Best Value Model Variables on Contractor Selection Decision", International Organization Of Scientific Research, 2014 More
  • Ahmed Hessien Mahmoud Mohamed Elyamany, "Utilizing Random Performance Records in the Best Value Model", Taylor & Francis, 2012 More
  • Ahmed Hessien Mahmoud Mohamed Elyamany, "Contractor Performance Evaluation for the Best-Value of Superpave Projects", ASCE, 2010 More

Department Related Publications

  • Ahmed Abdelaaty Gaballah Elsayaad, "Finance-Based Scheduling of Construction Projects Using Integer Programming", Journal of Construction Eng. and Management, ASCE, 2004 More
  • Ashraf Mohamed Mohamed Attia Elazony, "Finance-Based Scheduling of Construction Projects Using Integer Programming", Journal of Construction Eng. and Management, ASCE, 2004 More
  • Hossameldien Hosny Mohamed Badie, "Optimum Organization Structure for Construction Projects (Management Tool for Selecting Organization in the Egyptian Construction Market)", IJESIT, 2013 More
  • Hossameldien Hosny Mohamed Badie, "Construction Claims Causes and Management Efficiency", Engineering Research Journal, Faculty of Engineering , Mataria, Cairo., 2013 More
  • Hossameldien Hosny Mohamed Badie, "Evaluation of Change Management Efficiency of Construction Contractors", Housing and Building Research Center (HBRC) Journal , Elsevier., 2013 More
Tweet