Management of construction cost contingency covering upside and downside risks

Faculty Engineering Year: 2014
Type of Publication: ZU Hosted Pages: 863-881
Authors:
Journal: Alexandria Engineering Journal Alexandria Engineering Journal Volume: Alexandria Engineering Journal (2014) 53,
Keywords : Management , construction cost contingency covering upside , downside    
Abstract:
Many contractors are of the opinion that adding contingency funds to the tender price of a project may lead to loss of the tender. This research is a trial to put an end to this incorrect opinion. A more mature attitude to risk would recog
   
     
 
       

Author Related Publications

  • Hossameldien Hosny Mohamed Badie, "Optimum Organization Structure for Construction Projects (Management Tool for Selecting Organization in the Egyptian Construction Market)", IJESIT, 2013 More
  • Hossameldien Hosny Mohamed Badie, "Construction Claims Causes and Management Efficiency", Engineering Research Journal, Faculty of Engineering , Mataria, Cairo., 2013 More
  • Hossameldien Hosny Mohamed Badie, "(Effect of Inadequate Site Investigation on the Cost of Road Construction (Case Study", Engineering Research Journal, Faculty of Engineering , Mataria, Cairo., 2012 More
  • Hossameldien Hosny Mohamed Badie, "Effect of Re- Organization on the Performance of the Egyptian Economical Organization for Water and Waste water.", Engineering Research Journal, Faculty of Engineering , Mataria, Cairo., 2013 More
  • Hossameldien Hosny Mohamed Badie, "Evaluation of Change Management Efficiency of Construction Contractors", Housing and Building Research Center (HBRC) Journal , Elsevier., 2013 More

Department Related Publications

  • Ahmed Elsayed Ali Mahmoud, "An Integrated Sustainable Construction Project’s Critical Success Factors (ISCSFs)", Sustainable Engineering and Science, 2021 More
  • Gamal Saber Ahmed Elfiky, "Determination of local gravimetric geoid model over Egypt using LSC and FFT estimation techniques based on different satellite- and ground-based datasets", Taylor & Francis, 2021 More
  • Mohammed Ahmed Ali Alashkar , "Determination of local gravimetric geoid model over Egypt using LSC and FFT estimation techniques based on different satellite- and ground-based datasets", Taylor & Francis, 2021 More
  • Ahmed Hussien Ibrahim Mahmmoud, "Management of Construction Cost Contingency Covering Upside and Downside Risks.", Alexandria Engineering Journal (AEJ),, 2014 More
Tweet